State-run NHPC today said it has synchronised a 50 MW solar PV project at Theni/Dindigul district of Tamil Nadu with the grid.

The project was synchronised with the grid last month in presence of the commissioning team consisting of senior officers from TANGEDCO and the NHPC project officials, an NHPC statement said.

The Power Station has generated 6.87 MU (million units) up to April 15, 2018. The solar project shall provide an annual generation of 105 MU with sale of entire power to the TANGEDCO in accordance with the power purchase agreement.